the attached assignment below is to calculate the total standard time.
the formula is ( setup time + run time = total time (standard hours))
Calculating the Load 5.13
Instructions: A work center has the following open and planned orders for week 4. Calculate the total standard time required (load).
Work Center Orders
|
Order Quantity |
Setup Time (hours) |
Run Time (hours/piece) |
Total Time (hours) |
|||||
Released Orders: 120 |
300 |
1.00 |
0.10 |
||||||
340 |
200 |
2.50 |
0.30 |
||||||
Planned Orders: 560 |
3.00 |
0.25 |
|||||||
780 |
500 |
2.00 |
0.15 |
||||||
Total Time (standard hours) |